Cyber Park Karawaci
nro.constructionhq@linknet.co.id
Target Vs Achievement B2S
Summary Progress B2S
Target vs Achievement B2S
Monthly Achievement :
422 / 15,000
Yearly Achievement :
48,430 / 200,000
Success Rate :
24%
Monthly Ach P1 Ver 1.0 :
-
Monthly Ach P1 Ver 2.0 :
-
Monthly Ach P1 Ver 3.0 :
-
Monthly Ach P1 Ver 4.0 :
-
Monthly Ach P1 Ver 5.0:
-
Monthly Ach Finish PO Released :
-
Monthly Ach CQT :
-
Yearly Ach :
-
Yearly Target :
-
Success Rate :
-
Key Performance Indicators (B2S)
Waiting Complete Lv.1
460,257 / 460,770
99.9%
Waiting BAST Lv.2
459,540 / 460,257
99.8%
BAUT
453,573 / 473,230
95.8%
Project Closing
8,684 / 9,333
93%
Preparation
Actual SKOM – Min Actual Start
(AVG Days)
18
Construction
Min Actual Start – Max Actual Finish
(AVG Days)
126
Documentation
Max Actual Finish – Memo Date
(AVG Days)
39
Complete Project
Memo Date – Complete Project
(AVG Days)
0
Waiting Complete Lv.1
66,006 / 66,006
100%
Waiting BAST Lv.2
65,151 / 66,006
98.7%
BAUT
42,612 / 47,607
89.5%
Project Closing
8,684 / 9,333
93%
Waiting Complete Lv.1
66,006 / 66,006
100%
Waiting BAST Lv.2
65,151 / 66,006
98.7%
BAUT
41,751 / 49,606
84.2%
Project Closing
8,684 / 9,333
93%
Preparation
Actual SKOM – Min Actual Start
(AVG Days)
25
Construction
Min Actual Start – Max Actual Finish
(AVG Days)
269
Documentation
Max Actual Finish – Memo Date
(AVG Days)
142
Complete Project
Memo Date – Complete Project
(AVG Days)
20